Greetings,
In last week's update from Justin Smart, he informed you that your weekly 800 North updates would be coming from me at
chulet@langdongroupinc.com. Justin and I are working together on the project, but the contact phone remains the same (801-360-4944). If you would like to contact us via email, feel free to email Justin or me at any time.
Sincerely,
Carri Hulet800 North Public Information Team
chulet@langdongroupinc.comwww.udot.utah.gov/orem800north801-360-4944
Changes are coming on the 800 North project this week, including shifting westbound traffic to the north side of the road between 400 East and 800 East. Please take note of the coming construction activities listed below, and exercise particular caution in the work zone in the coming weeks as traffic shifts and temporary lane closures change the flow of traffic. Provided weather and other scheduling issues cooperate, crews hope to shift all traffic to the newly paved north side of the road from 400 West to 800 East the week of Oct. 22. Details will be provided in the coming weeks’ updates. Please note that for your safety, pedestrian traffic should use the south side of 800 North for the time being. Even though sidewalk is being placed along the northern side of the road, construction activities in this area continue to pose potential safety hazards to pedestrians.
Thanks to all for your patience with construction activities. The project team is very aware of the inconvenience and delay the project causes and is working to keep progress moving.
Construction Activity Update – 10/12/07
The following are planned activities for the coming week. Please note that due to weather, project conflicts, or equipment/supply issues, schedules are subject to change.
400 West Intersection: Paving in this area should be complete by the weekend, with final signal pole placement taking place next week. Crews hope to activate this signal by the end of October. Please watch for workers in the area.
400 West to State Street: Paving along the north side of the road in this area is substantially complete for now. Crews plan to place sidewalk and concrete driveways in this area during the week of Oct. 15.
Canal Crossing at 375 East: Crews plan to begin work on the canal beneath 800 North, located at approximately 375 East, the week of Oct. 15. Reconstruction and paving in this area has been on hold pending the end of the irrigation season. With canal irrigation scheduled to end on the 15th, crews plan to finalize the roadway work on the north side of 800 North in this area as quickly as possible.
400 East to 750 East: Sunday,
Oct. 14, crews plan to shift westbound traffic to the north side of 800 North, onto the new pavement. Westbound traffic will shift to the north just west of the 800 East intersection and remain on the north side until just west of the 400 East intersection. Eastbound traffic in this section will remain on the far south side of 800 North, with crews working in the middle all week. Please use extra caution and reduce speeds in the area for your safety and the safety of the construction crews. On Monday, Oct. 15, eastbound traffic in this section will be restricted to one lane to accommodate asphalt removal operations. Watch for flaggers in this area Monday. By Tuesday, eastbound traffic should be back to two lanes. Tuesday, Oct. 16, through Friday, Oct. 19, crews plan to prepare the middle section of road for new asphalt and pave. Even as left-hand turns have been restricted in this area for some time, please be aware that lefts remain restricted given work that will take place in the middle of the road and given the fact that the old pavement will be lower than the new pavement.
Sound Wall Installation: Installation of two wall sections remains pending as various property and utility issues are resolved. Wall staining and other finish work will proceed this week on installed sections.
Water Line Installation at 1000 East: Crews are installing a water line in the area of 1000 East. Please be aware of traffic shifts and intermittent lane restrictions in the area through the end of next week.
More Information
Project updates and background can be found online at
www.udot.utah.gov/orem800north. This site will be updated as the project continues and details become available. For specific questions or concerns, contact the Public Information Team at 801-360-4944 or by email at
chulet@langdongroupinc.com.